Raymangirr Access Road cyclone repairs

Contract value: $526,890
Start date: August 2016
Date for completion: October 2016
Contractor: NT Feral Pig Harvesting

 

The Raymangirr Access Road runs 47km from the Gapuwiyak Barge Road to the Raymangirr outstation.

Raymangirr road was severely effected by the intense rain event associated with Cyclone Nathan recording 540mm through the month of February (near half being recorded in a single day).  Deep longitudinal and transverse scouring occurred in numerous sections with further creek crossing washing away.

With valuable funding through the Natural Disaster Recovery and Relief Arrangement we seek to repair this roadway. The works generally comprise of road repairs namely the reformation, gravel patching and drainage works